Background
The Practivistas Domincana Program is currently a study abroad program involving Humboldt State University and UNIBE that takes place in Santo Domingo, Domincan Republic. The rainwater catchment system in Las Malvinas in Santo Domingo was first constructed in 2011 by Intelegencia Colectivo from UNIBE. The water from this system was used for washing but was not potable.
Objective
Vandalism and two years of wear and tear has caused the system to fail in its purpose to collect rainwater. The goal is to return the system to working condition and to improve on the previous design.
Literature Review
Literature reviews from La Yuca rainwater catchment (2013) (2012) (2011) were utilized to understand and reconstruct the rainwater catchment system in Las Malvinas.
Criteria
Criteria | Constraints | Weight (1-10) |
---|---|---|
Accessibility | ||
Level of Maintenance | ||
Water Demand | ||
Educational | ||
Safety | ||
Time | ||
Materials | ||
Cost | ||
Durability |
Timeline
June 28th 2013
Went to Las Malvinas to look at the school rainwater catchment system. Ended up with an alternative project to fix the rainwater catchment system in the Play.
June 29th 2013
Bought materials for the rainwater catchment system in the Play in Las Malvinas. Fixed the toilet/sink system, and first flush. The first screening still has to be modified.
June 30th 2013
Started Construction on the Play rainwater catchment system.
- Removed roof
- Fixed bent sections of the roof
- Disassembled the rainwater catchment system
- Cleaned the tinaco
July 1st 2013
- Rain
July 2nd 2013
- Rain
July 3rd 2013
- Worked on constructing the roof
- Worked on completing powerpoint for our project presentation
July 4th 2013
- Presentation on our projects
July 5th 2013
- Sancocho and dancing in Las Malvinas
July 6th 2013
- Installed the PVC gutters
- Drilled a hole into the cap of the tinaco for the PVC inlet
- Created the primary screening
- Finished constructing and gluing the first flush
July 7th 2013
- Completed project with the addition of a faucet and adding silicone to a leak.
Final Design
Budget
Material | Quantity | Material Cost (DOP) | Total Cost (DOP) |
---|---|---|---|
1" T PVC | 1 | Donated | 0 |