The refrigerator arrived after all the project participants had left Parras. The only remaining HSU student, Jeff Kinzer, agreed to do the installation. | The refrigerator arrived after all the project participants had left Parras. The only remaining HSU student, Jeff Kinzer, agreed to do the installation. | ||
The | The SunFrost refrigerator arrived at the Muñíz residence on Monday, August 1. The refrigerator remained there while we searched for a truck to carry the package to the hospital. By the time I was able to get access to a truck, the refrigerator had already been moved. Upon going to Centro de Salud Fridady August 5, I was informed that no one would be in the laboratory until Monday. I returned Monday to discover the refrigerator had been installed by Antonio, the hospital technician. | ||
The refrigerator is fully installed and working. Currently (18:09, 7 August 2006 (PDT)), the unit is set at 40° F. There is no method for monitoring the internal temperature. Tomorrow, August 8th, Antonio will be installing a thermometer in order to measure the refrigerator for a week before using the system for vaccines. Antonio reports that the solar panels are maintaining 13.16V. | The refrigerator is fully installed and working. Currently (18:09, 7 August 2006 (PDT)), the unit is set at 40° F. There is no method for monitoring the internal temperature. Tomorrow, August 8th, Antonio will be installing a thermometer in order to measure the refrigerator for a week before using the system for vaccines. Antonio reports that the solar panels are maintaining 13.16V. |