m (Text replacement - "| affiliations = " to "| organizations = ")
 
(44 intermediate revisions by 8 users not shown)
Line 1: Line 1:
<!-- Comments that appear only in the edit view are formatted like this. -->
[[File:las malvinas first screening.jpg|thumb]]
<!-- These comments are offered as an aid as you get started. Remove as you wish. -->
<!-- next line is the code for inserting an image; delete if you don't have an image yet -->
{{template:Practivistas Dominicana student projects header}}
{{TOCright}}


[[File:Imageneeded.png|thumb|right|Sample photo caption.]]
{{Project data
| authors = User:Amp123
| status = Deployed
| completed = 2013
| location = Las Malvinas, Santo Domingo, Dominican Republic
}}


{{Practivistas Dominicana menu}}


[[File:las malvinas rainwater catchment system.jpg|thumb|Rainwater team working on cleaning and reconstructing the roof]]


== Background ==
The Practivistas Domincana Program is currently a study abroad program involving Cal Poly Humboldt and UNIBE that takes place in Santo Domingo, Domincan Republic. The rainwater catchment system in Las Malvinas in Santo Domingo was first constructed in 2011 by Intelegencia Colectivo from UNIBE. The water from this system was used for washing but was not potable.
The Practivistas Domincana Program is currently a study abroad program involving Humboldt State University and UNIBE that takes place in Santo Domingo, Domincan Republic. The rainwater catchment system in Las Malvinas in Santo Domingo was first constructed in 2011 by Intelegencia Colectivo from UNIBE. The water from this system was used for washing but was not potable.


== Objective ==
== Objective ==
Vandalism and two years of wear and tear has caused the system to fail in its purpose to collect rainwater. The goal is to return the system to working condition and to improve on the previous design.
Vandalism and two years of wear and tear has caused the system to fail in its purpose to collect rainwater. The goal is to return the system to working condition and to improve on the previous design.


== Literature Review ==
== Literature Review ==


==Criteria==
Literature reviews from [[La Yuca rainwater catchment 2013|La Yuca rainwater catchment]] ([[La Yuca rainwater catchment 2013#Literature Review|2013]]) ([[La Yuca rainwater catchment 2012#Literature Review|2012]]) ([[La Yuca rainwater catchment 2011#Literature Review|2011]]) were utilized to understand and reconstruct the rainwater catchment system in Las Malvinas.
{| class="wikitable sortable"
 
|-
== Criteria ==
 
{| class="wikitable"
! Criteria
! Criteria
! Constraints
! Constraints
! Weight <br>(1-10)
! Weight<br>(1-10)
|-
|-
| Accessibility
| Accessibility
| <center>Convenient location for everything</center>
| Convenient location for everything
| <center>8</center>
| 8
|-
|-
| Level of Maintenance  
| Level of Maintenance
| <center>Necessary < 3X a year </center>
| Necessary < 3X a year
| <center>8</center>
| 8
|-
|-
| Water Demand
| Water Demand
| <center>enough to wash clothes for a few families</center>
| enough to wash clothes for a few families
|<center>8- depends on rain</center>
| 8- depends on rain
|-
|-
| Educational  
| Educational
| <center>at least 1 person</center>
| at least 1 person
|<center>7</center>
| 7
|-
|-
| Safety
| Safety
|<center> Must be sturdy and clean enough for washing</center>
| Must be sturdy and clean enough for washing
|<center>9</center>
| 9
|-
|-
| Time
| Time
| <center>finish project before we leave</center>
| finish project before we leave
|<center>10</center>
| 10
|-
|-
| Materials
| Materials
| <center> Materials are all local</center>
| Materials are all local
| <center>8</center>
| 8
|-
|-
| Cost
| Cost
| <center>as inexpensive as safely possible</center>
| as inexpensive as safely possible
| <center>8</center>
| 8
|-
|Durability
|<center>Long lasting design</center>
|<center>8</center>
|-
|-
| Durability
| Long lasting design
| 8
|}
|}
== Final Design ==
The final design of the rainwater catchment system in Las Malvinas consisted of reconstruction of the roof and first flush. Additionally a primary screening and PVC gutters were included in the design. The outcome consisted of a working rainwater catchment system that efficiently prevents contaminants from entering the tinaco(water storage tank).
<gallery>
File:Las malvinas roof construction.jpg|Reconstruction of the roof
File:Las malvinas first screening.jpg|Finished Rainwater catchment system
</gallery>
=== Maintenance ===
This final design requires consistent upkeep in order to reduce the amount of contaminants.
''Periodically OR Every Few Rainfalls''
* First Flush holes should be cleared of any blockage
''Every Month''
* Primary screening must be checked for damage or clogging
''Every Year''
* First Flush must be thoroughly cleaned
* Tinaco (or storage tank) must be emptied of sediment and disinfected
* Sediment must be replaced
==== Maintenance Video ====
Refer to the La Yuca rainwater catchment [[La Yuca rainwater catchment 2013#Maintenance Video|2013]] maintenance video for guidance on how upkeep a rainwater catchment system.


== Timeline ==
== Timeline ==


== Final Design ==
'''June 28th 2013'''
Went to Las Malvinas to look at the school rainwater catchment system. Ended up with an alternative project to fix the rainwater catchment system in the Play.
 
'''June 29th 2013'''
Bought materials for the rainwater catchment system in the Play in Las Malvinas.
Fixed the toilet/sink system, and first flush. The first screening still has to be modified.
 
'''June 30th 2013'''
Started Construction on the Play rainwater catchment system.
 
* Removed roof
* Fixed bent sections of the roof
* Disassembled the rainwater catchment system
* Cleaned the tinaco
 
'''July 1st 2013'''
 
* Rain
 
'''July 2nd 2013'''
 
* Rain
 
'''July 3rd 2013'''
 
* Worked on constructing the roof
* Worked on completing powerpoint for our project presentation
 
'''July 4th 2013'''
 
* Presentation on our projects
 
'''July 5th 2013'''


== Budget ==
* Sancocho and dancing in Las Malvinas


'''July 6th 2013'''


* Installed the PVC gutters
* Drilled a hole into the cap of the tinaco for the PVC inlet
* Created the primary screening
* Finished constructing and gluing the first flush


<!-- Here is a sample gallery.  -->
'''July 7th 2013'''
<gallery caption="Sample gallery">
File:Imageneeded.png|Sample caption text.
File:Imageneeded.png|More sample caption text. This would look better with different images. :)
File:Imageneeded.png|Even more sample caption text.
</gallery>


* Completed project with the addition of a faucet and adding silicone to a leak.


{{Page data
| keywords = rainwater, rainwater catchment, pvc
| sdg = SDG06 Clean water and sanitation, SDG11 Sustainable cities and communities, SDG12 Responsible consumption and production
| published = 2013
| organizations = Practivistas Dominicana Program, Cal Poly Humboldt
| license = CC-BY-SA-3.0
| language = en
}}


[[Category:Projects]]
[[Category:Practivistas Dominicana Program]]
[[Category:Practivistas Dominicana Program]]
[[Category:Rainwater]]

Latest revision as of 11:56, 28 February 2024

Las malvinas first screening.jpg
FA info icon.svg Angle down icon.svg Project data
Authors Andres Pineda
Location Las Malvinas, Santo Domingo, Dominican Republic
Status Deployed
Completed 2013
OKH Manifest Download
Rainwater team working on cleaning and reconstructing the roof

The Practivistas Domincana Program is currently a study abroad program involving Cal Poly Humboldt and UNIBE that takes place in Santo Domingo, Domincan Republic. The rainwater catchment system in Las Malvinas in Santo Domingo was first constructed in 2011 by Intelegencia Colectivo from UNIBE. The water from this system was used for washing but was not potable.

Objective[edit | edit source]

Vandalism and two years of wear and tear has caused the system to fail in its purpose to collect rainwater. The goal is to return the system to working condition and to improve on the previous design.

Literature Review[edit | edit source]

Literature reviews from La Yuca rainwater catchment (2013) (2012) (2011) were utilized to understand and reconstruct the rainwater catchment system in Las Malvinas.

Criteria[edit | edit source]

Criteria Constraints Weight
(1-10)
Accessibility Convenient location for everything 8
Level of Maintenance Necessary < 3X a year 8
Water Demand enough to wash clothes for a few families 8- depends on rain
Educational at least 1 person 7
Safety Must be sturdy and clean enough for washing 9
Time finish project before we leave 10
Materials Materials are all local 8
Cost as inexpensive as safely possible 8
Durability Long lasting design 8

Final Design[edit | edit source]

The final design of the rainwater catchment system in Las Malvinas consisted of reconstruction of the roof and first flush. Additionally a primary screening and PVC gutters were included in the design. The outcome consisted of a working rainwater catchment system that efficiently prevents contaminants from entering the tinaco(water storage tank).

Maintenance[edit | edit source]

This final design requires consistent upkeep in order to reduce the amount of contaminants. Periodically OR Every Few Rainfalls

  • First Flush holes should be cleared of any blockage

Every Month

  • Primary screening must be checked for damage or clogging

Every Year

  • First Flush must be thoroughly cleaned
  • Tinaco (or storage tank) must be emptied of sediment and disinfected
  • Sediment must be replaced

Maintenance Video[edit | edit source]

Refer to the La Yuca rainwater catchment 2013 maintenance video for guidance on how upkeep a rainwater catchment system.

Timeline[edit | edit source]

June 28th 2013 Went to Las Malvinas to look at the school rainwater catchment system. Ended up with an alternative project to fix the rainwater catchment system in the Play.

June 29th 2013 Bought materials for the rainwater catchment system in the Play in Las Malvinas. Fixed the toilet/sink system, and first flush. The first screening still has to be modified.

June 30th 2013 Started Construction on the Play rainwater catchment system.

  • Removed roof
  • Fixed bent sections of the roof
  • Disassembled the rainwater catchment system
  • Cleaned the tinaco

July 1st 2013

  • Rain

July 2nd 2013

  • Rain

July 3rd 2013

  • Worked on constructing the roof
  • Worked on completing powerpoint for our project presentation

July 4th 2013

  • Presentation on our projects

July 5th 2013

  • Sancocho and dancing in Las Malvinas

July 6th 2013

  • Installed the PVC gutters
  • Drilled a hole into the cap of the tinaco for the PVC inlet
  • Created the primary screening
  • Finished constructing and gluing the first flush

July 7th 2013

  • Completed project with the addition of a faucet and adding silicone to a leak.