|description=Our objective for the water project for the 2014 Practivistas Dominicana Program in La Yuca is to replace the flat piping system, used to catch rainwater runoff from the roof, with a gutter that will obtain more water.
|intended-use=development, industry
|keywords=
|project-link=
|contact-affiliation=
|contact-appropedia-user=User:Jacob Burns
|image=Layucafirstflush2014.jpg
|development-stage=
|made=No
|made-independently=No
|derivative-of=
|manufacturing-files=
|manifest-language=eng
|date-published=
|main-materials=
|sustainable-development-goal=Sustainable Development Goal 8, Sustainable Development Goal 10, Sustainable Development Goal 12
|documentation-language=eng
}}
<!--end infobox-->
==Abstract==
[[File:Layucafirstflush2014.jpg |thumb| left| First flush system]]
[[File:Layucafirstflush2014.jpg |thumb| left| First flush system]]
==Abstract==


<center>''Our project consisted of analyzing and restoring the existing rainwater catchment system located at La Yuca’s school. After repairs were completed, our group expanded the existing system and developed an easily accessible rainwater catchment system that captures, filters, and distributes water that can be used by the local community. It is our goal that available rainwater can be captured efficiently and filtered sufficiently to be used for faucet and toilet purposes, thus providing the community with a cost effective solution to their water shortage.''</center>
<center>''Our project consisted of analyzing and restoring the existing rainwater catchment system located at La Yuca’s school. After repairs were completed, our group expanded the existing system and developed an easily accessible rainwater catchment system that captures, filters, and distributes water that can be used by the local community. It is our goal that available rainwater can be captured efficiently and filtered sufficiently to be used for faucet and toilet purposes, thus providing the community with a cost effective solution to their water shortage.''</center>

Revision as of 14:38, 14 June 2020

Template:TOCleft

FA info icon.svg Angle down icon.svg Device data
Hardware license CERN-OHL-S
Certifications Start OSHWA certification

Abstract

First flush system
Our project consisted of analyzing and restoring the existing rainwater catchment system located at La Yuca’s school. After repairs were completed, our group expanded the existing system and developed an easily accessible rainwater catchment system that captures, filters, and distributes water that can be used by the local community. It is our goal that available rainwater can be captured efficiently and filtered sufficiently to be used for faucet and toilet purposes, thus providing the community with a cost effective solution to their water shortage.
Roof for catchment

Background

This appropriate technology project is located in Dominican Republic in the La Yuca neighborhood of Santo Domingo. The student team includes 3 students from Humboldt State University and 4 students from UNIBE and the project is taking place in the month of June, 2014. Concurrent to the project, the Humboldt State students are taking classes at UNIBE in Santo Domingo. The classes are focused on appropriate technology and engineering and are paired with one Spanish class. The system in La Yuca is a rainwater catchment system which has been developed by previous groups over the last three years. The system has not been successful in consistently capturing rainwater and fully utilizing the storage tank attached to the system. The system is attached to the local school and it is a priority of the school to have running water and ideally potable drinking water.

Objective

Our objective for the water project for the 2014 Practivistas Dominicana Program in La Yuca is to replace the flat piping system, used to catch rainwater runoff from the roof, with a gutter that will obtain more water. The extra water will be fed into an additional storage tank.

Criteria

Below is a table of the criteria used to evaluate project components and make decisions.

Criteria: Constraints Weight
Aesthetics Must satisfy aesthetic desires of community. 5
Cost Must be within budget constraints of our project. 8
Locality Must use materials found within the community of La Yuca. 3
Durability The structure must last at least 3 years. 8
Replicability Ability to be remade by another or same community. 8
Safety Sound structure and mosquito proof. 9
Potable Drinkable water, this includes removal of sedimentation, pathogens, and viruses. 10

Literature Review

Here is the link for the information we collected to help us understand and review information that will allow us to build the appropriate rainwater catchment system in La Yuca for the 2014 practivistas dominicana program.

Location

An Interactive Map for La Yuca. The small cluster of buildings is the rural community where the rainwater catchment is located.

Loading map...

Construction

Cost

The table below is a summary of the materials and their associated costs which were used for this upgrade of the La Yuca rainwater catchment system. It should be noted that these costs do not represent the entire costs of the rainwater system, for we only upgraded that catchment part of the system and did not build the distribution system throughout the school house. The previous appropedia pages can be referenced for more cost information.

Material Quantity Unit Cost (DOP) Total Cost (DOP)
PVC Gutter [9 ft.] 3 1600 4800
Carbon FIlters 2 250 500
Nylon Filters 2 160 320
Botellon [5 gal.] 1 195 195
Botellon PVC adapter [2] 1 31.12 31.12
Bag of screws [25 mm.] 1 42.00 42.00
Bag of screws [40mm.] 1 47.00 47.00
Outdoor L-brackets 6 75 450
Gutter [9 ft] 3 1,963 5,890
Plastic mesh for botellon [6 Yrd.] 1 48.12 48.12
Metal mesh for gutter [1 Yrd.] 1 289.17 289.17
Gutter connector 2 168.00 336.20
Tinaco [530 gal] 1 6,700 6,700
90 degree turn for gutter 1 520.10 520.10
Total Cost 20,168.71

Buy Back

This graph illustrates the time it would take for this system to pay itself back in the form of drinkable water. This system will pay itself off in less than a year assuming that the system will catch and use 60% of all rainfall for each given month. Assumed at 30,000 DOP because the system in la yuca was not complete, but rather added to; therefore a complete system would cost roughly 30,000 DOP. The system adds 850 DOP every year to take filter replacement costs into account.

Reupdatedbuyback2014layuca.png

Timeline

To ensure productivity, efficiency, and the ability to recreate this project it is essential to propose a course of action. This is done by proposing dates that certain tasks should be completed by; the dates these tasks were actually completed should also be recorded.

Task: Date Proposed Date Done
Analyze existing rainwater catchment system in an attempt to locate issues Wednesday June 11, 2014 Wednesday June 11, 2014
Disassemble existing rainwater catchment system Thursday June 12, 2014 Thursday June 12, 2014
Thoroughly clean and disinfect piping that will be used on future rainwater catchment system Thursday June 12, 2014 Thursday June 12, 2014
Remove non-functioning gutter/piping system Thursday June 12, 2014 Thursday June 12, 2014
Clean and store non-functioning gutter Thursday June 12, 2014 Thursday June 12, 2014
Create design to correct existing problems on system Friday June 13, 2014 Friday June 13, 2014
Get an advance on our budget in order to have the ability to purchase materials Friday June 13, 2014 Friday June 13, 2014
Take necessary measurements in order to perform calculations to prove that design would work Saturday June 14, 2014 Saturday June 14, 2014
Visit various ferreterias in order to purchase and transport necessary materials Saturday June 14, 2014 Saturday June 14, 2014
Find and rent needed tools, including a power drill that can be used to drill into cement columns Sunday June 15, 2014 Monday June 16, 2014
Obtain power tools to drill holes into first flush system, this will allow water to flow out slowly subsequently eliminating mosquito breeding in first flush system Monday June 16, 2014 Monday June 16, 2014
Purchase metal needed to secure gutter system to L-brackets Monday June 16, 2014 Monday June 16, 2014
Design, create, and install "parrales" to secure gutter system to L-brackets Monday June 16, 2014 Monday June 16, 2014
Install new gutter/piping system Tuesday June 17, 2014 Tuesday June 17, 2014
Reconstruct intake system (5 gallon botellon) Tuesday June 17, 2014 Tuesday June 17, 2014
Reconnect intake system to first flush system Wednesday June 18, 2014 Wednesday June 18, 2014
Connect gutter to intake Wednesday June 18, 2014 Wednesday June 18, 2014
Run tests to test design, system, and its efficiency Wednesday June 18, 2014 Wednesday June 18, 2014
Purchase metal and plastic to construct curtain that will prevent rainwater from spilling over the gutter, eliminating water loss and increasing efficiency Thursday June 19, 2014 Thursday June 19, 2014
Purchase additional water storage tank (tinaco) in order to provide more than 5 days of water storage Thursday June 19, 2014 Monday June 23, 2014
Install additional tank to existing system Friday June 20, 2014 Tuesday June 24, 2014
Reconnect entire rainwater catchment systems Friday June 20, 2014 Tuesday June 24, 2014
Flush out entire system with water in order to clean and eliminate any sediments that have been accumulated throughout building process Saturday June 21, 2014 Tuesday June 24, 2014
Clean and organize location which houses rainwater catchment system Saturday June 21, 2014 Tuesday June 24, 2014
Run tests to test design, system, and its efficiency Saturday June 21, 2014 Wednesday June 25, 2014

Design

The design plan for the rainwater catchment system can be referenced in the model below. The design was done in Google Sketchup and represents the exact system for which our team built off of.

Google Sketchup of system: Alberto Jasso.
Google Sketchup of system: Alberto Jasso.

Maintenance

This system needs maintenance year-round to ensure that everything works properly and stays clean, especially when taking into account cleanliness of a potable system.

Weekly

  • Make sure the botellon screen is clean
  • Make sure there isn't too much debris in the gutter
  • Make sure the first flush isn't clogged and water is able to drain to avoid mosquito breeding. Our team re-poked small holes that were previously clogged in the first flush to make sure water was able to drain out of the system after rain. Make sure the holes are too big that the first flush doesn't fully fill up.

Monthly

  • Clean the first flush system
  • Check for leaks
  • Make sure the roof is clean (no debris on the roof)


Yearly/Biyearly

  • Clean the tinaco
  • Buy new filters Biyearly

How We

File:La yucawire2014.jpg
Steps to Ensure a Proper Catchment System

To replace filters refer to this table to find AQUA-TEC.

AQUA-TEC La Julia,
Santo Domingo de Guzman 10107
Republica Dominicana
info@aquatec.com.do
809-732-1572
Aquatec website

Videos

Inspirational Trailer!

Error in widget YouTube: Unable to load template 'wiki:YouTube'

Maintenance of first flush.

Error in widget YouTube: Unable to load template 'wiki:YouTube'

Team

The Water Team 2014. Alberto Jasso, Jake Burns Arlene Alejo.