Timeline
|Scope out project area
|Get a feel for the space, start to come up with prototype ideas
|2-26-19February 26th, 2019|3-5-19March 5th, 2019
|-
|Create prototypes
|Come up with different routes to take on this project, focus on placement of rainwater system components, design for desire and function
|3-10-19March 12th, 2019|3-12-19March 12th, 2019
|-
| Meet with CCAT | Talk with them about their goals of the rainwater catchment and discover end goals of rainwater| 3-26-19March 26th, 2019|March 27th, 2019| 3-27-19|Weekly CCAT meetings|Attend weekly CCAT meetings to discuss project progress, improvements, and feedback |Weekly|Weekly
|-
|Start to gather materials
|Look through supplies at CCAT and find things that we can use for the catchment system|March 12th, 2019|March 27th, 2019|3-3|Meet with Risk Management|Lonny ended up becoming the spokesperson when it came to facilities management and met with them on our behalf|April 1st, 2019|Varies|-13|3Start construction|Break ground on our project, brought in river rocks|March 26th, 2019|April 4th, 2019|-17|Continue construction|Continue to build rainwater catchment system, keep adding to system and striving for excellence |April 2nd, 2019|April 5th, 2019|-13|Meeting with Lonny|Have Lonny come look at the progress of the project and provide any feedback, feedback included getting rid of the wood pallet that the storage tanks were on|April 9th, 2019|April 9th, 2019|- |Catch up with other groups|Get updates and progress reports, help each other if possible and learn from one another to improve everyone's projects as much as possible to ensure a positive working/learning environment|April 16th, 2019|May 1st, 2019|-|Finish presentation and Video|Ensure that the video shows all attributes of the system and clearly communicates the project, the goal, and the design|April 30th, 2019|May 13th, 2019|-|Work on Appropedia final draft|Make sure formatting is clean, clear, and to the point|April 30th, 2019|May 13th, 2019|-|Wrap-up construction and finishing touches |Make sure that the project works and is completed to the best of the teams abilities|May 7th, 2019|May 15th, 2019
|-
|}
 
 
'''Week 8:'''
*Possible buying of construction materials
*Meet with risk management and facilities at school to make sure we can begin working at CCAT
*Meet with CCAT
*Meet with Lonny
 
'''Spring Break'''
 
'''Week 9:'''
*Project Photos
*Meet with CCAT
*Meet with Lonny
*Catch up with other groups and see if we can learn from/help each other
*Start Construction
*Work on appropedia page
 
'''Week 10:'''
*Observations and Interviews II
*Meet with CCAT
*More Construction
*Work on appropedia page
 
'''Week 11:'''
*Appropedia Draft page done
*Meet with CCAT
*Meet with Lonny
*Construction
 
'''Week 12:'''
*Timesheet #4
*Meet with CCAT
*Construction
*Catch up with other groups and see how they are doing to help each other with projects
 
'''Week 13:'''
*Meet with CCAT
*Meet with Lonny
*Construction
*Work on appropedia page more
 
'''Week 14:'''
*Talk with class as a whole about project updates and see if anyone has any ideas for ours
*Meet with CCAT
*Begin working on Appropedia final draft
*Begin work on final presentation and videos
 
'''Week 15:'''
*Final presentation due
*Finish final video
==Cost==