Bayside Park Farm solar dehydrator

172 bytes added, 03:54, 12 May 2014
{| class="wikitable sortable"
|-
! Estimated
Completion Date
! Completion Date
! Task
|-
| 2/02/14
| 2/02/14
| Began setting up Appropedia page.
|-
| 2/08/14
| 2/08/14
| Chose two designs to begin prototyping.
|-
| 2/14/14
| 2/14/14
| Met with client in order to determine specific requirements for dehydrator.
|-
| 2/20-2/22/14
| 2/20-2/22/14
| Constructed two prototypes from cardboard and cellophane wrap; conducted 1 day of testing.
|-
| 3/02/14
| 3/02/14
| Began accumulating materials for full-size construction and possible wood prototypes.
|-
| 3/14/14 | Finish 3/09/14 | Finished prototype constructiontesting
|-
| 3/16-3/22/14
| N/A
| Prototype testing in Southern California or Hawaii (spring break destinations) in order to determine effectiveness. Source materials for final design.
|-
| 3/23/14
| 3/24/14
| Determine dimensions and parts necessary for final design.
|-
| 3/26/14
| 3/28/14
| Finish sourcing materials for final design. Begin construction of final design.
|-
| 4/18/14
| 4/20/14
| Finish construction of final design.
|-
| 4/10-4/19/14| 4/22-4/30/14
| Trial runs of design in order to determine flaws and necessary improvements
|-
| 4/20-4/30/14
| 5/05/14
| Fix flaws, final trial run. Record results.
|-
| 5/01/14
| 5/05/14
| Finish testing effectiveness of various solar absorbers
|-
| 5/11/14
| 5/11/14
| Deliver dehydrator to Bayside Park Farm.