No edit summary
mNo edit summary
Line 213: Line 213:
[[Category:Rainwater]]
[[Category:Rainwater]]
[[Category:Projects]]
[[Category:Projects]]
==Update October 2017==
Interviewed Natalie about how the the catchment system is doing.
Overall health of the system is great, everything from the first flush to the storage.
Currently using the water for watering plants in the garden.
The system is doing great and satisfying their current needs; a future system is not currently on their radar.
[[File:The Black Hole Storage 1.jpg]]
Picture of the Black hole in October 2017.

Revision as of 04:16, 16 October 2017


Secondary storage and plumbing

Abstract

A rainwater catchment system was designed and constructed at The Sanctuary in Arcata, CA. This project was completed for Humboldt State University class, ENGR 215 FALL 16, and is a collaboration between four students. The catchment system can hold up to 900 gallons of captured rainwater. A 55 gallon drum is used as the secondary storage. A 850 gallon pond acts as the primary storage for the system. The pond is covered with a bridge, for walking or storage, and the pond contains an overflow drain.

Background

Sacred Consulting is a team of four students in the Fall 2016 semester of ENGR 215 at Humboldt State University consists of: Jenna Davey, Karen Duarte, Richard Thompson, and Caleb Wegner. This group chose to design and construct a rainwater catchment system for the client. The client for this project is The Creative Sanctuary, a local non-profit art facility who promotes green technology, art, community involvement and sustainable living. Even though this client has one rainwater catchment system on the property already, there are 2 gutters currently not being used for collection.

Problem statement and criteria

Criteria and constraints are a set of useful guidelines to refer to when deciding which design best fits the needs of the client.

Problem Statement

The Creative Sanctuary has two rain gutters that are not being used to collect the water, and would like to use one or both of them as inputs to a rainwater catchment system.

Criteria

Below is a table that displays the criteria laid out to assist in the decision making process.

Criteria Importance Constraints
Sustainability 9 Obtain the lowest embedded energy for each item in the system.
Cost 8 Spend less than $400.
Usefulness 8 Storage capacity must provide at least 25% of the water for the garden and other outdoor uses.
Maintenance 8 Maintenance must require less than 1hr per week.
Aesthetics 7 look as good or better than the surrounding structures.
Accessibility 5 The area must still be available to foot traffic.
Sizing 4 Water storage must match the volume of the water coming into the system.

Description of final project

Photos and descriptions.


Cost Table

The costs in hours for this project are listed below. The total hours spent by the team both designing and implementing the system is 150 hrs.

The monetary costs of this project are minimal considering the amount of donated materials which came from the client, The Sanctuary. The total cost of the system is $83.88 and a breakdown of the cost of each item can be seen below.

Quantity Material Source Cost ($) Total ($)
1 15' x 15' Black Pond Liner Donated 0.00 0.00
13 ft. 2" Black ABS Pipe Donated 0.00 0.00
32 ft. 3" Black Corrugated Drain Pipe Donated 0.00 0.00
1 55 gallon Blue PVC barrel w/ White Lid Donated 0.00 0.00
1 3" Black Corrugated Drain Elbow Fitting Donated 0.00 0.00
1 1/2 Plastic Tubing Donated 0.00 0.00
179" 3" Black ABS Pipe Donated 0.00 0.00
ABS Adhesive Donated 0.00 0.00
ABS Primer Donated 0.00 0.00
3 3" ABS Tee Fitting Ace Hardware 7.99 23.97
6 3" ABS 90 (degrees) Elbow Fitting Ace Hardware 6.99 41.94
1 2" Adapter Ace Hardware 1.99 1.99
2 3" to 2" Couple flex Fitting Ace Hardware 7.99 15.98
Total Cost $83.88

Testing Results

The system is currently filling up and storing water, but has not had the chance to provide water to the garden because the rain has been sufficient enough up to this point in time.

How to build

In order to replicate the rainwater catchment system that was built for the Sanctuary, follow the steps below. YOU WILL NEED A SHOVEL.

File:Black hole in progress.jpg
How to build a rainwater catchment system

Maintenance

"The Black Hole" was designed to need as little regular maintenance as possible. Due to this there is only an estimated 7 hours per year in required maintenance. The breakdown of what tasks need to be done and the estimated cost are shown below.

Schedule

Every year the system needs a complete cleaning and winterization. This annual cleaning should be performed in the fall of the year before the rains start. This allows the system to be as clean as possible before filling with water. If the entire system needs to be cleaned and the pond is full of water, that water must be emptied so that the pond liner can be removed to be cleaned. While the total cleaning time can vary, cleaning the pond liner should only take one hour if all the water has been removed.


The other task that will need to be completed is the emptying and cleaning of the first flush water diverter and the secondary tank. Occasionally, this first flush diverter will become clogged with debris and sediment. Time needed to empty and clean the first flush water diverter and secondary storage is estimated to take less than one half of an hour. This maintenance is recommended to be performed once a month.


In total the system should require under 7 hours of maintenance per year.

Monthly
  • Empty and clean secondary storage
  • Empty and clean first flush diverter
Yearly
  • Remove/Clean/Replace pond liner
  • Flush all pipes and clean gutters

Troubleshooting

This is only how to troubleshoot basic operation. For complex issues, contact Lonny Grafman (HSU).

Problem Suggestion
Water is not flowing into the pond. Check flow by putting a hose into the gutter and find clogged area.
Water is dirty. First flush diverter is not draining properly.
Pond wall integrity Too much water in area surrounding the pond.

Discussion and next steps

References

See Help:Footnotes for more. Template:Reflist

Poster

Rainwater Catchment Poster 1.jpg

Update October 2017

Interviewed Natalie about how the the catchment system is doing. Overall health of the system is great, everything from the first flush to the storage. Currently using the water for watering plants in the garden. The system is doing great and satisfying their current needs; a future system is not currently on their radar. The Black Hole Storage 1.jpg Picture of the Black hole in October 2017.

Cookies help us deliver our services. By using our services, you agree to our use of cookies.